Roof cross-section — drawn to your numbers
Standard pitchFor every 12 inches the roof runs horizontally, it rises 9 inches.
Roof pitch chart: 1/12 to 24/12
Every standard pitch converted to angle, slope % and slope factor, plus the 18/12 and 24/12 rows for steep mansard and A-frame roofs. The row nearest your pitch is highlighted as you use the calculator — screenshot this chart and you can convert any pitch on a job site without the tool.
| Pitch | Angle | Slope | Slope factor | Rafter per 12″ run | Category |
|---|---|---|---|---|---|
| 1/12Nearly flat | 4.76° | 8% | ×1.003 | 12.04 in | Nearly flat |
| 2/12Low slope | 9.46° | 17% | ×1.014 | 12.17 in | Low slope |
| 3/12Low slope | 14.04° | 25% | ×1.031 | 12.37 in | Low slope |
| 4/12Standard pitch | 18.43° | 33% | ×1.054 | 12.65 in | Standard pitch |
| 5/12Standard pitch | 22.62° | 42% | ×1.083 | 13.00 in | Standard pitch |
| 6/12Standard pitch | 26.57° | 50% | ×1.118 | 13.42 in | Standard pitch |
| 7/12Standard pitch | 30.26° | 58% | ×1.158 | 13.89 in | Standard pitch |
| 8/12Standard pitch | 33.69° | 67% | ×1.202 | 14.42 in | Standard pitch |
| 9/12Standard pitch | 36.87° | 75% | ×1.250 | 15.00 in | Standard pitch |
| 10/12Steep pitch | 39.81° | 83% | ×1.302 | 15.62 in | Steep pitch |
| 11/12Steep pitch | 42.51° | 92% | ×1.357 | 16.28 in | Steep pitch |
| 12/12Steep pitch | 45.00° | 100% | ×1.414 | 16.97 in | Steep pitch |
| 18/12Very steep | 56.31° | 150% | ×1.803 | 21.63 in | Very steep |
| 24/12Very steep | 63.43° | 200% | ×2.236 | 26.83 in | Very steep |
Slope factor (also called the pitch multiplier) converts a horizontal run into the length measured along the slope: 14 ft of run under a 9/12 roof needs 14 × 1.250 = 17.50 ft of rafter. The rafter column is that same hypotenuse over a 12-inch run, before ridge and birdsmouth deductions.
Which roofing materials your pitch allows
Pitch is not a style choice — it decides what can legally and safely go on the roof. Shingles shed water by overlap, not by being waterproof, so below certain pitches water backs up under them. Check your pitch against this table, then against the IRC R905 minimums by covering in the next section.
| Pitch range | Category | Works well | Watch out |
|---|---|---|---|
| 0.25/12 – 2/12 | Nearly flat | Membrane (TPO / EPDM), modified bitumen, built-up roofing, standing-seam metal rated for low slope | Asphalt shingles are not allowed — water ponds and migrates under laps |
| 2/12 – 4/12 | Low slope | Metal panels, rolled roofing; shingles only with full ice-and-water shield or double underlayment | Standard single-underlayment shingle jobs fail early here — and most warranties exclude them |
| 4/12 – 9/12 | Standard | Asphalt shingles, metal, concrete/clay tile, slate, cedar shake — the full menu | Tile and slate are heavy: confirm the framing is rated for the load |
| 9/12 – 12/12 | Steep | Shingles with 6 nails per shingle, metal, slate with extra fastening | Not walkable without roof jacks and harnesses — plan access and fall protection before anyone goes up |
| Over 12/12 | Very steep | Siding-style applications, mansard cladding, standing seam | Snow and ice shed fast and land hard — plan gutters and snow guards |
The code minimum for each covering is listed in the IRC R905 table below (asphalt shingles: 2/12 absolute minimum with double underlayment, 4/12 for standard application). A manufacturer's installation manual can require a steeper pitch than code — where the two differ, the steeper figure governs.
Minimum roof pitch by covering: IRC R905
Section R905 of the International Residential Code (Roof Assemblies) sets the shallowest slope each covering may be installed on. Find your pitch in the calculator above, then check it against the covering you want — if your pitch is below the covering's minimum, that covering is not a code-compliant option on your roof.
| Roof covering | IRC section | Minimum pitch | Conditions |
|---|---|---|---|
| Asphalt shingles | R905.2 | 2/12 | From 2/12 to under 4/12, double underlayment is required (R905.1.1). At 4/12 and over, standard single-underlayment application applies. |
| Clay & concrete tile | R905.3 | 2½/12 | From 2½/12 to under 4/12, double underlayment is required (R905.1.1). |
| Metal roof shingles | R905.4 | 3/12 | Installed over solid sheathing with underlayment per R905.1.1. |
| Mineral-surfaced roll roofing | R905.5 | 1/12 | Laps cemented and fastened per the manufacturer's instructions. |
| Slate shingles | R905.6 | 4/12 | Steepest shingle-type minimum in R905 — slate relies on slope to shed water. |
| Wood shingles | R905.7 | 3/12 | Solid or spaced sheathing; exposure limits tighten as pitch drops. |
| Wood shakes | R905.8 | 3/12 | Interlayment felt required between courses. |
| Built-up roofing | R905.9 | ¼/12 | Coal-tar built-up roofs are the one exception, permitted down to ⅛/12. |
| Metal panels — standing seam | R905.10 | ¼/12 | The sealed seam is what allows panel metal to run this shallow. |
| Metal panels — lapped, with sealant | R905.10 | ½/12 | Lapped, non-soldered seams with lap sealant applied. |
| Metal panels — lapped, no sealant | R905.10 | 3/12 | Without sealant the lap alone must shed water, so the minimum jumps to 3/12. |
| Modified bitumen | R905.11 | ¼/12 | Membrane system — positive drainage still required. |
| Thermoset single-ply (EPDM) | R905.12 | ¼/12 | Membrane system — positive drainage still required. |
| Thermoplastic single-ply (TPO / PVC) | R905.13 | ¼/12 | Membrane system — positive drainage still required. |
| Sprayed polyurethane foam | R905.14 | ¼/12 | Foam plus protective coating, applied to a sloped deck. |
| Photovoltaic shingles | R905.17 | 2/12 | Same floor as the asphalt shingles they replace. |
Source: International Residential Code, §R905 (Roof Assemblies) and §R905.1.1 (underlayment). These are code minimums, not recommendations — a manufacturer's installation instructions can require a steeper pitch, and local amendments vary, so confirm with your building department before ordering a covering.
How to measure a roof pitch you already have
You don't need to climb anything to get an accurate rise and run. All three methods measure the same triangle — pick the one that matches what you can safely reach.
From the attic — most accurate
Hold a level against the underside of a rafter and mark 12 inches along it from where it meets the rafter. Measure straight down from that mark to the rafter — that vertical distance is your rise. No weather, no shingle thickness, no guessing.
With a speed square — on the roof
Hook the square's lip over the top edge of a rafter tail or the ridge, let the pivot point settle, and read the “common” scale where the edge crosses. That number is the x in x/12 directly. Only do this if you can already work on the roof safely.
Phone level — from the ground
Stand at the gable end, hold your phone's edge along the rake (the sloped trim board) and read the angle from an inclinometer app. Enter it under Angle ° above. Accurate to about half a pitch step — good enough to identify the roof and check it against the R905 minimums.
Pitch to Angle Calculator: Roof Pitch Formulas
Nothing here is a black box — this roof pitch calculator runs on one right triangle, rise, run and rafter, and every number on this page comes from these four formulas.
A 5-inch rise over a 12-inch run is a 5/12. Measured over any other run, scale it: 10 inches of rise over 24 of run is the same 5/12.
Arctan converts the ratio into degrees. 9/12 → arctan(0.75) = 36.87°. This is the number a speed square, saw bevel and inclinometer all speak.
Pythagoras in disguise: the rafter length over a 1-unit run. Multiply a horizontal run by it to get the true length along the slope — at 9/12, each foot of run takes 1.25 ft of rafter.
Use the full horizontal run the rafter covers — half the building span plus the overhang. 14 ft of run at 9/12 → 14 × 1.250 = 17.50 ft of rafter.
A 9/12 roof on a 26 ft wide house, by hand
The calculator's default numbers, worked step by step so you can check them with a pencil.
Rise 9 in over run 12 in. Slope = 0.75 × 100 = 75%, and the pitch is 9/12.
arctan(0.75) = 36.87° — the bevel setting for every rafter cut on this roof.
√(1 + 0.75²) = √1.5625 = 1.250. Each foot of run needs 12 × 1.250 = 15.00 in of rafter.
Half the 26 ft span is 13 ft, plus a 12 in overhang = 14 ft of run. 14 × 1.250 = 17.50 ft — 17 ft 6 in of common rafter, and the ridge sits 13 × 0.75 = 9.75 ft above the wall plate.
Four pitch mistakes that cost money
✕ Reading slope % as degrees
A 50% slope is 26.6°, not 50°. Percent and degrees only agree at 0. A full 45° roof is a 100% slope — a 12/12. Mixing these up doubles or halves every angle you cut.
✕ Measuring over the shingles
Tape laid on the roof surface includes shingle thickness and any sag, and it measures the rafter, not the rise. Measure the triangle — level plus vertical — from the attic or a rafter tail instead.
✕ Forgetting the overhang in rafter length
A rafter doesn't stop at the wall. Half-span alone gives a rafter that's a foot or more short on a typical eave — order on half span + overhang, then deduct for the ridge board and birdsmouth.
✕ Assuming both sides match