20 × 10 ft slab · 4 in thick · 2.47 yd³ exact + 10% waste, rounded up to the nearest ¼ yard.
Short-load warning2.75 yd³ is under a full 9 yd³ truck, so the plant may charge a short-load fee. The $95 delivery / short-load fee in the editable prices is included in this estimate — confirm the exact fee with your plant before ordering.
Plan view — drawn to scale
How This Concrete Slab Calculator Works
The maths is simple; the judgement is in the allowances. The concrete slab calculator multiplies length × width × thickness to get cubic feet, adds the thickened-edge trench volume when the edge is switched on, divides by 27 for cubic yards, then adds your waste percentage and rounds ready-mix orders up to the nearest quarter yard — the smallest step most plants will batch. The single bag line on the ticket is a secondary figure worked from that same volume with waste, using the true yield of each bag size (0.60 ft³ for 80 lb, 0.45 ft³ for 60 lb) — it is there for small hand-mixed pours, not as the way to order a slab.
Underneath the slab it also sizes the parts people forget to order: the compacted gravel base (same footprint, at the depth you set), the 6-mil vapour retarder required under floor slabs by IRC R506.2.3 (slab area plus 10% for the 6-inch laps, counted in 10 × 100 ft rolls), a #4 rebar grid at your chosen spacing with lap allowance, wire mesh sheets as the light-duty alternative, and form boards around the full perimeter. Cost combines the concrete itself, delivery, base, vapour retarder, the reinforcement you select and forms — plus pro labour and finishing when you select a pro pour — and shows a range, because soil, access and local plant prices move the real number.
The thickened edge is the volume most calculators leave out. A garage or footing slab is not a flat plate: a trench around the perimeter — typically 12 inches wide and 12 inches deep — carries the load down to firm soil. Only the part of the trench below the slab's own thickness is extra concrete, and the corners are counted once, not twice. On a 24 × 20 ft slab that edge adds 56 ft³ — about a quarter of the whole pour — and leave it out and the truck runs dry before the last bay is filled.
Edge volume (ft³) = (perimeter − 4 × edge width) × edge width × (edge depth − slab thickness), all in feet
Cubic yards = (slab + edge) ft³ ÷ 27 · Order yards = exact yards × (1 + waste %) rounded ↑ to nearest 0.25
Gravel base (yd³) = length × width × base depth (in) ÷ 12 ÷ 27 · Forms (LF) = 2 × (length + width)
Vapour retarder = slab area × 1.10 for laps, in 10 × 100 ft rolls · Mesh sheets = area × 1.10 ÷ 50 sq ft (5 × 10 ft sheet)
Rebar (LF) = rows both directions × bar length, + 10% for laps and chairs
Slab Concrete Calculator: How Thick Should the Slab Be?
Thickness is the cheapest insurance you can buy — one extra inch on a 20×10 slab is only about 0.6 of a yard. Match the thickness to what the slab will carry, and put steel in anything a vehicle will touch.
Code minimum — IRC R506.1: a concrete floor slab supported directly on the ground must be not less than 3.5 inches thick. That 3.5 in figure is a floor, not a design target: every recommendation in the table below sits at or above it, and the calculator's standard slab is 4 in. Exterior flatwork such as patios and walkways is not all covered by R506.1, and local amendments can require more — but no slab in this guide goes below the code floor.
| Use | Thickness | Reinforcement | Notes |
|---|---|---|---|
| Code minimum — floor slab on ground (IRC R506.1) | 3.5 in min | As designed | Legal floor for a slab supported directly on ground — not a load recommendation |
| Walkway, patio, shed base | 4 in | Wire mesh or fibre | The standard light-duty slab |
| Hot tub pad | 6 in | #4 rebar, 18 in grid | A filled tub can weigh 2 tons |
| Driveway — cars & SUVs | 5–6 in | #4 rebar, 24 in grid | Thickened edge where wheels turn in |
| Garage floor | 4–6 in | #4 rebar, 18–24 in grid | Thickened edge 12 in deep + 6-mil vapour retarder (IRC R506.2.3) |
| RV pad, trucks, dumpster pad | 6–8 in | #4–#5 rebar, 12–18 in grid | Point loads crack thin slabs |
| Basketball / sport court | 4 in | Wire mesh | Control joints every 8–10 ft |
Code Thickness Guide — IRC R506.1 in Plain Terms
Section R506 covers concrete floors (slabs on ground). Read with R506.2, it sets the build-up this calculator prices: a prepared base, the 3.5 in minimum slab, and — for floor slabs inside a building — the 6-mil vapour retarder of R506.2.3.
| What the code covers | Requirement | What this page uses |
|---|---|---|
| Minimum slab thickness — IRC R506.1 | Not less than 3.5 in for a concrete floor slab supported directly on the ground | 4 in standard default; 5–6 in driveways; 6 in or more for heavy loads — all above the minimum |
| Base course — IRC R506.2.2 | 4 in base course of clean graded sand, gravel, crushed stone or similar under the slab (exceptions apply) | 4 in compacted gravel base by default (editable depth) |
| Vapour retarder — IRC R506.2.3 | 6-mil polyethylene (or equivalent) between the base or subgrade and the floor slab, joints lapped at least 6 in | 6-mil poly allowed at slab area + 10% for laps, counted in 10 × 100 ft rolls |
| Thickened edge / footing slabs | Edge depth and width are set by the footing and frost requirements for the building, not by R506.1 | Optional 12 × 12 in edge by default (editable width and depth), volume added before waste |
Code is a minimum standard, not a guarantee against cracking: soil, drainage, steel placement and curing decide how a slab performs. Where a local amendment or an engineer's design calls for a thicker slab, that thicker figure governs.
Ready-Mix Truck First — Live Cost Comparison
These figures follow your slab above, and the ready-mix truck is the default way to pour one. The crossover is usually around 1 cubic yard: below it, the delivery and short-load fee makes the truck expensive and hand-mixing is the sensible secondary route; above it, hand-mixing costs more per yard and a big slab can go cold before you finish mixing it.
Short-load fees: a standard mixer drum carries about 9 cubic yards, and most plants charge a short-load fee — commonly $50–$150 — when an order falls well short of a full load, on top of the delivery charge. The ticket above warns you whenever your order is under a full 9 yd³ truck, and the $95 delivery / short-load fee in the editable prices is already included in the estimate; confirm the exact fee with your plant, because minimum-load rules vary.
| Route | Concrete cost | Mixing time | Best for |
|---|---|---|---|
| Ready-mix truck | $549 | Placed in ~1 hr | Slabs over 1 yd³, driveways, anything structural |
| Hand-mixing from bags + rented mixer (secondary route) | $689 + mixer hire | ≈ 6–8 hrs mixing | Small pads, remote sites, no truck access |
Verdict for this slab: the truck wins — hand-mixing this volume is a full day of work, and a slab this size needs to be placed and finished in one continuous pour.
Worked Example: a 24 × 20 ft Garage Slab With a Thickened Edge
Slab volume: 24 × 20 × (4 ÷ 12) = 160 ft³ (5.93 yd³). Thickened edge: the trench is 12 in wide and 12 in deep, so it adds 8 in of depth below the slab around an effective perimeter of 84 ft (88 ft of perimeter, corners counted once): 84 × 1 × (8 ÷ 12) = 56 ft³ — a 35% increase on the slab alone, and about 26% of the total pour. Total exact volume: 160 + 56 = 216 ft³ → 216 ÷ 27 = 8.00 yd³. Add 10% waste → 237.6 ft³ (8.80 yd³), rounded up to the nearest quarter yard: order 9 yd³, not 8. Ordering the exact 8 leaves nothing for a dipping subgrade — and ignoring the edge entirely would have you order just 6.75 yd³ and run more than 2 yards short mid-pour. Set the calculator above to 24 × 20 ft with the thickened edge switched on and it returns exactly these figures.
At 9 yd³ the order fills one standard drum, so no short-load fee applies beyond the standard delivery charge. Underneath: a 4-inch gravel base over 480 sq ft is 5.9 yd³; the 6-mil vapour retarder (IRC R506.2.3) needs 480 × 1.10 = 528 sq ft, one 10 × 100 ft roll; a #4 rebar grid at 24 inches takes 577 LF (29 × 20 ft bars) — or, if you run 6×6 wire mesh instead, 11 sheets of 5 × 10 ft; form boards run the full 88 ft perimeter. Cost: 9 yd³ at $165 plus the $95 delivery fee is $1,580 of concrete; gravel, vapour retarder, rebar and forms bring materials to $2,561, and a pro pour-and-finish at $4.25/sq ft ($2,040) puts the estimate at $4,049 – $5,153, with a $4,601 mid ($9.58/sq ft). Secondary line only: the same volume with waste ÷ 0.60 = 396 × 80 lb bags (÷ 0.45 = 528 × 60 lb bags) — nearly 16 tons of dry mix to mix by hand, which is why this slab goes on a truck. For bag-only jobs like fence posts and footings, use the Concrete Bag Calculator instead.
Six Slab Mistakes That Cost Real Money
Ordering the exact maths
The excavated hole is always deeper somewhere. Exact-volume orders run short mid-pour, and a second short load costs more than the spare quarter yard would have. Keep 10% waste on every order.
Skipping the gravel base
Concrete poured on bare soil settles unevenly and wicks moisture. Four inches of compacted gravel is cheap, drains the slab, and is the difference between a 5-year and a 25-year patio.
Steel lying on the ground
Rebar or mesh sitting on the base does nothing — it has to sit in the middle third of the slab on chairs or dobies. Mesh that gets walked down during the pour is the most common wasted material on site.
No control joints
Concrete will crack; joints decide where. Cut or tool joints every 8–12 ft (and within 24 hours if saw-cutting) so shrinkage cracks run in straight lines instead of across the middle of your slab.
Forgetting the thickened edge
A flat-plate calculation under-orders any slab with a turned-down edge. On a 24 × 20 ft garage slab the 12 × 12 in edge trench holds 56 ft³ — running short by that much, mid-pour, means a second delivery, a short-load fee and a cold joint across your floor.
No vapour retarder indoors
Flooring laid over a slab with no 6-mil poly under it (IRC R506.2.3) can fail from moisture vapour within a year — cupped timber, lifting vinyl, musty carpet. The roll costs little; it cannot be added once the concrete is down.
Sources & Assumptions — Reviewed 26 November 2026
Every number this calculator produces rests on the figures below. Prices are 2026 US national benchmarks for planning, all of them editable in the calculator — confirm the ones that matter with your local ready-mix plant and yard before ordering. Last reviewed: 26 November 2026.
| Item | Figure used on this page | Source / basis |
|---|---|---|
| Minimum slab thickness | 3.5 in minimum; 4 in standard default | IRC R506.1 — concrete floor slab supported directly on ground, not less than 3.5 in |
| Vapour retarder | 6-mil poly, area + 10% for laps, 10 × 100 ft rolls at $65 | IRC R506.2.3 — 6-mil polyethylene, joints lapped at least 6 in; roll price is a 2026 benchmark |
| Base course | 4 in compacted gravel (editable), priced at about $48 per yd³ placed in the estimate | IRC R506.2.2 — 4 in base course under the slab; price is a 2026 benchmark |
| Ready-mix concrete | $165 per yd³, orders rounded up to the nearest 0.25 yd³ | BuildPriceCalc 2026 US national benchmark, reviewed 26 November 2026 |
| Delivery / short-load fee | $95 included per load; typical short-load fees run $50–$150 | BuildPriceCalc 2026 benchmark range; exact fee varies by plant — confirm before ordering |
| Truck capacity | 9 yd³ standard drum; short-load warning below 9 yd³ ordered | Standard ready-mix drum size used across this page |
| Waste allowance | 10% default (editable 0–30%) | Industry practice for spillage, pump priming and uneven subgrade |
| Bag yields (secondary line only) | 80 lb bag = 0.60 ft³; 60 lb bag = 0.45 ft³ | Standard manufacturer yields for pre-mixed concrete bags |
| Reinforcement | #4 rebar on a 24 in grid + 10% for laps; mesh in 5 × 10 ft sheets + 10% for laps at $13 per sheet | Calculator defaults (grid spacing and sheet price editable); sheet size is the standard retail size |
| Thickened edge | 12 in wide × 12 in deep default; only the depth below the slab counts as extra volume, corners counted once | Typical turned-down edge dimensions; width and depth editable in the calculator |
| Pro labour & finishing | $4.25 per sq ft; estimate shown as mid ± 12% range | BuildPriceCalc 2026 US national benchmark, reviewed 26 November 2026 |
| Worked example check | 24 × 20 ft garage slab, 12 × 12 in edge: 8.00 yd³ exact, order 9 yd³ | Worked through in full in the example above; the calculator returns the same figures at those settings |
Assumptions the calculator does not make: it does not price excavation, demolition of an old slab, permits, pumping beyond standard placement, coloured or stamped finishes, or frost-depth footings deeper than the edge depth you enter. Add those locally where they apply.
Concrete Slab Calculator — Frequently Asked Questions
How much concrete do I need for a 20×10 slab?
At 4 inches thick, 2.47 cubic yards before waste. With the standard 10% allowance this concrete slab calculator rounds the order to 2.75 cubic yards of ready-mix — a part-load in one 9 yd³ truck — over a 4-inch gravel base (about 2.5 yd³) with a #4 rebar grid (about 254 LF) inside 60 LF of form boards.
How does a concrete slab calculator work out cubic yards?
Length × width × thickness in feet gives cubic feet; dividing by 27 converts to cubic yards. The calculator then adds waste and rounds up to the nearest quarter yard, because subgrades are never perfectly level and plants batch in quarter-yard steps.
How thick should a concrete slab be?
Start from the code floor: IRC R506.1 requires a concrete floor slab supported directly on the ground to be at least 3.5 inches thick — a minimum, not a target. In practice, 4 inches for patios, walkways and shed bases; 5–6 inches for driveways; 6 inches or more with rebar for garages, RV pads and hot tubs. Going one inch thicker costs little — on a 20×10 slab, roughly 0.6 of a yard — and prevents most load cracks.
What else do I need besides concrete for a slab?
A slab is more than the pour. A 20×10 ft slab also needs a 4-inch compacted gravel base (about 2.5 yd³), a #4 rebar grid at 24 inches (about 254 LF, 13 × 20 ft bars) or 5 sheets of 5 × 10 ft wire mesh, 60 LF of form boards, and — under an indoor or garage floor — a 6-mil vapour retarder (220 sq ft, one 10 × 100 ft roll). Bag counts appear on the batch ticket as one secondary line for small hand-mixed pours; for bag-only jobs such as fence posts and footings, use the dedicated Concrete Bag Calculator.
Is ready-mix or bagged concrete cheaper?
Hand-mixing from bags wins under about half a cubic yard, because ready-mix carries a delivery and short-load fee. Above 1–2 yards the truck is cheaper per yard and places in about an hour what hand-mixing takes all day — and a slab placed in one continuous pour is stronger than one built up in cold joints.
Do I need gravel and rebar under a concrete slab?
For almost every slab, yes. A 4-inch compacted gravel base prevents settling and frost heave, and rebar or mesh held in the middle third of the slab keeps shrinkage cracks tight. The calculator includes both in the material list and the cost.
How much extra concrete does a thickened edge add?
More than most people expect. The edge is a trench around the perimeter — typically 12 in wide and 12 in deep — and only the part below the slab's own thickness is extra. On a 24 × 20 ft garage slab at 4 in thick, a 12 × 12 in edge adds 56 ft³: the slab alone is 160 ft³ (5.93 yd³), the exact total becomes 216 ft³ (8.00 yd³), and with 10% waste you should order 9 yd³, not 8. Switch the thickened edge on in the calculator and set its width and depth to match your trench.
Do I need a vapour retarder under a concrete slab?
For floor slabs inside a building, yes. IRC R506.2.3 calls for a 6-mil polyethylene vapour retarder between the base course or subgrade and the concrete floor slab, with joints lapped at least 6 in. This calculator allows 10% extra for laps and trimming — a 24 × 20 ft slab needs 528 sq ft, which is one 10 × 100 ft roll — and includes the roll in the cost when the vapour retarder is switched on. Under an outdoor patio it is optional.
What is a short-load fee on ready-mix concrete?
It is the fee a ready-mix plant charges when your order is smaller than a full truck. A standard drum carries about 9 yd³, and many plants set their minimum load well below that; small orders commonly carry a $50–$150 short-load fee on top of delivery. This calculator includes a $95 delivery / short-load fee in its editable prices and warns you on the batch ticket whenever the order is under a full 9 yd³ truck — confirm the exact fee with your plant before ordering.
Should I use rebar or wire mesh in a concrete slab?
Use a #4 rebar grid for driveways, garage floors and any slab carrying vehicles or a thickened edge — it holds cracks tight and ties the edge into the slab. 6×6 welded wire mesh in 5 × 10 ft sheets suits light-duty patios and walkways and is faster to place, as long as it is chaired up into the middle third of the slab rather than left on the base. The calculator counts both — rebar in linear feet and 20 ft bars, mesh in 5 × 10 ft sheets with 10% for laps and cutting — and costs whichever you select, or both together.
What is the minimum concrete slab thickness allowed by code?
3.5 inches. IRC R506.1 requires a concrete floor slab supported directly on the ground to be not less than 3.5 inches thick. That is the code minimum for a floor slab on ground, not a recommendation for load: this page's standard light-duty slab is 4 inches, driveways are 5–6 inches, and heavy or vehicle slabs are 6 inches or more with rebar. Exterior slabs such as patios and walkways are not all covered by R506.1, but none of the thicknesses in the guide on this page go below the 3.5 inch floor.
When were the prices and assumptions on this page last reviewed?
26 November 2026. The sources and assumptions table above lists every figure the calculator uses and where it comes from: minimum thickness 3.5 inches per IRC R506.1, 6-mil vapour retarder with 6-inch laps per IRC R506.2.3, ready-mix at $165 per cubic yard and a $95 delivery / short-load fee from BuildPriceCalc 2026 US national benchmarks, bag yields of 0.60 ft³ for an 80 lb bag and 0.45 ft³ for a 60 lb bag, a 10% waste allowance, a 9 yd³ standard truck, and pro labour and finishing at $4.25 per sq ft. All prices are editable — confirm them with your local plant and yard before ordering.